July 18, 2020
Bridge deck forms and supports

July 11, 2020
Granite curb delivery to the site

July 4, 2020
View of the work zone

June 27, 2020
De-watering the flooded work zone

June 20, 2020
Placement of reinforcing steel for the bridge deck

June 13, 2020
Canal wall mortar matching with the National Park Service

June 6, 2020
Form work erection for bridge deck

May 30, 2020
Installation of Pepco conduits

May 23, 2020
Continued removal of canal wall supports

May 16, 2020
Delivery and installation of beams

May 9, 2020
Removal of the canal wall support

May 2, 2020
Adding rebar at the pier footing

April 25, 2020
Placement of concrete at south abutment

April 18, 2020
Storing removed canal wall stone in the canal

April 11, 2020
Continued back wall excavation and canal wall stone removal

April 4, 2020
Continued back wall excavation and canal wall stone removal at the south abutment

March 28, 2020
Back wall excavation and canal wall stone removal at South abutment

March 21, 2020
Demolition of Pepco concrete duct banks

March 14, 2020
Installation of Verizon cables

March 7, 2020
Current site conditions

February 29, 2020
Current site conditions

February 22, 2020
Connecting new Pepco conduit to new manhole.

February 15, 2020
Micropile load testing at the north abutment.

February 8, 2020
Ongoing utility relocations